Electricity generated through coal plants is becoming expensive by every passing day and Power cuts
and increasing dependence on DG sets is causing a lot of damage to the environment, keeping this in
mind as per Ministry of New and Renewable Energy (MNRE), Government of India we at MODY
PUMPS (INDIA) PVT.LTD. installed 20Kw capacity a grid-tie solar rooftop in photovoltaic (PV) system
where electricity generated by solar cells mounted on roof top of factory.
System converts solar electric (PV) into utility grade electricity which converts solar energy into direct
current (DC) which is fed into power grid.
Details:
Installed Capacity: 20 Kw
Total Cost of the project: 1468400 INR
Date of installation: 10.12.2015
Customer Code :2383 (MNRE SPIN)
Net metering system as per agreement with MSEDCL Kalyan MH.